1, abide by cast installation current operating rules.
2, whether is point of examination platen entry touched with slideway photograph, if be touched, answer to be handled in time.
3, nod first move test-drive, run for nothing next 2-3 minute, examination transmission system (electromotor, shaft coupling, reducer) the motion with platen is smooth, after affirming everything is normal, fangke has production.
4, when clearing every time, the load of spare parts be clearinged is 250~350 kilogram, every weight does not exceed 2.5 kilograms.
5, when driving, receive first on aspiration conduit, next actuate tumbling barrel; When jockeying, stop tumbling barrel first, aspiration canal is pulled open after.
6, during equipment actuate, if discover platen is pinned,block annulus, should inform maintenance technician is adjusted, lest cause plain bearing liner,give out heat or burned-out plain bearing liner.