1, abide by " cast installation current operating rules " concerned regulation.
2, examination pipeline system one day flat circumstance rises with what play air cylinder fall circumstance, after deciding everything is normal, fangke has production.
3, before the job, start first fanner and carriage leather belt, use device again next.
4, when clip runs modular group, must leave ejector pin center to going up, in lest be in,shaking, modular group falls off or fly off.
5, after modular group clip has been held, must close shake, must not open the door the job.
6, when using form of model of straight condole of overhead traveling crane, must not collide handle of cut down door.
7, discover handle is out of order or handle cannot move to need when the position, answer to undertake checking first, must not puissant pull move.
8, after the job, stop equipment first, stop carriage leather belt and fanner again.
9, air cylinder and clip are moved to hold air cylinder to add 20 mechanical oil to shake after the job, in case air cylinder and piston are unripe lure.
